It has been a very busy month for the Campaign Groups.
Reports from the National Audit Office, Ofgem consultations on Sea Link and LionLink, and the Public Accounts Committee inquiry have all raised significant questions about the planning, costs and value for money of the Great Grid Upgrade and other energy infrastructure.
On top of this, the Secretary of State (SoS) has made three requests for further information on Sea Link.
SEAS is preparing its response, due by 22 October, to National Grid’s brief answers to the SoS’s questions. Many important issues continue to remain unresolved, including:
• No completed Benhall bridge survey confirming whether it can accommodate the proposed heavy vehicles.
• No like-for-like comparison of Sea Link with the alternative proposed by SEAS.
• No confirmed solution to the harmonics problem, or clarity on whether additional network infrastructure will be needed.
• No confirmation that Sea Link can reliably deliver its intended 2GW capacity under the relevant operating conditions.
• No clear explanation of the substantial increase in project costs.
And these are just some of the outstanding questions.
Given their number and significance, how can the Secretary of State reach a properly informed decision by 31 October? SEAS has therefore requested an extension to allow adequate time for the outstanding matters to be considered.